Get a detailed real-world insight into Microsoft Project from accredited PM experts to help you plan and manage better projects.
| Course overview | |
| A general introduction into task and resource management using Microsoft Project for project managers and their teams. Step-by-step tutorials teach core skills, backed up by end of section exercises and multiple-choice questions to consolidate topics learned. | |
| Delivery method | |
| Virtual Classroom: 2 x 3 hours, Physical Classroom: 1 day. Available both In-Company (virtual & physical) and on our Public Course Schedule (virtual). | |
| Learning outcomes | |
After completing this course, delegates will be able to create common-sense project plans that model real-world project environments. They will:
|
|
| Audience | |
| Project Manager, Project Office Member, Resource Manager. | |
| Course detail | |
| What to do and how to do it
This initial section introduces the user to Microsoft Project, what it can (and cannot) do and why people use it. Smart ways to navigate the tool are introduced, together with how views and tables help keep all the project’s data organised. The overall scope of a project is then broken down into the tasks that will define it. These tasks are then managed within a hierarchical structure and linked to each other to create a schedule. This schedule is then reviewed to ensure that it accurately models the scope of the project and the benefits that the project is set to deliver. |
|
| Who does what and when
Section two looks firstly at how a project’s schedule of tasks and dates can be analysed to ensure that the project’s scope can be completed within a timely manner. Tools including views, tables and filters are employed to enhance and simplify this analysis process. With a workable project schedule determined, this section then explains how the project’s scope of work can be achieved by utilising resource effort. With resources realistically defined, assignments are then created to match tasks with the people to work against them. These assignments are then reviewed to ensure that all work planned has been allocated to resources best capable of carrying it out. |
|
| Optimising the project
This third section looks at how a project is influenced by the outside world and how it can be optimised to accurately measure reality. Working and non-working time is defined and its influence upon the project’s schedule is clearly seen. Tasks are constrained not only to each other, but also to dates determined by various project stakeholders. Resource utilisation options are examined to help determine supply vs. demand issues. Where resource conflicts exist, these are levelled to match work requirements with resource capacity. The impact of resource optimisation against the project’s schedule is investigated. |
|
| Progressing the project
This final section closes the loop by applying progress to the project and then determining the impact upon the project’s objectives as a result of this progress. A project is baselined to provide a reference point and version control is discussed to ensure accurate record keeping. Tasks are updated around a status date with start and finish dates and in-progress indications. Incomplete work is not overlooked and this is scheduled into the future. Variance analysis is performed to compare planned work with actual progress. The project is subsequently replanned to ensure that it remains on track. |
|
Want to find out more? Please complete the form below and we’ll get right back in touch.
Microsoft is a registered trademark of Microsoft Corporation. All other trademarks duly acknowledged.
