|
|
|
 |
Open one
of the following
project files as the background for this lesson: |
LESSON_B3_END.MPP |
your own project file |
|
LESSON_C1_START.MPP |
sample project file |
|
|
|
Walkthrough |
|
|
 |
|
4m 10s |
|
|
| |
|
| Using tables to show
specific information |
| |
|
| |
Like views, tables display specific information.
There are tables that relate to
task-based views and tables that relate to
resource-based views. The
Schedule table can be used to display when tasks can take place.
To display this table: |
|
|
| |
- From the View menu, select Table, and then select Schedule:

- Displaying schedule information about the project:

- The 'Design booth' task is
critical: Its
start and
late start
dates are the same, and it has a slack value of 0 days.
- The 'Create signage' task is
non-critical: There is a difference between its start and late
start dates and it has 10 days of
slack.
- The 'Prepare mailing list' task possesses 1
day of
free slack
and 16 days
total slack.
It could be delayed by up to 1 day without delaying any
successor
task and by up to 16 days overall without affecting the end date for
the project.
- The 'Post invitations' task possesses equal
amounts of free slack and total slack. This task can be delayed
by up to 15 days without affecting the schedule of any other task.
|
|
|
|
|
| |
| |
|
| Column insertion and
formatting |
| |
|
| |
Columns can be added or removed from table definitions. With the
Schedule table as described above, it would be useful to add the
Leveling Delay field. When the project has undergone resource
leveling, this field will indicate if any tasks have been delayed in
order to remove
resource conflicts. To add this field to the table: |
|
|
| |
- Click on a
column heading (to select the column)
to the right of where the new column is to be inserted:

- From the Insert menu, choose Column (or press
the INSERT key), creating a new blank column.
- Choose a field from the
drop down list:

- Confirm the insertion with OK.

|
|
|
|
|
|
|
Walkthrough |
|
|
 |
|
3m 07s |
|
|
| |
|
| Changing the way text
appears |
| |
|
| |
The appearance of text within a view can be changed
using buttons on the
formatting toolbar: fonts; font sizes; emboldening and so on. Whilst
this is okay for simple one-off changes, its results are often difficult
to interpret. As this could lead to confusion within the Trade Show
project, it has been decided to not allow any direct text formatting and
insist on the use of
text styles instead. The first text style to change is to
emphasize how
milestone tasks are displayed. To achieve this: |
|
|
| |
- From the Format menu, choose Text Styles.
- Select the item to change from the
drop down, then choose appropriate formatting:

- Confirmed with OK, to display as:

|
|
|
|
|
| |
| |
|
| Formatting the table's
rows |
| |
|
| |
An alternative to increasing a column's width is to
display cell information on more than one
row. If you have a project with a few tasks, but you want to
display lots of table columns, row heights can be changed:
- For individual rows (as below).
- For all rows by clicking on the
select all button,
then dragging the divider as below.
|
|
|
| |
- Select a row where text is too wide to fit within the current column
width:

- Drag the row divider below the row to
heighten:

- Displayed as:

|
|
|
 |
Differing row heights can make the chart part of a
view more difficult to read. |
|
| |
|
|
 |
|
|
|
|
|
|
 |
Save your project with the
following filename: |
LESSON_C1_END.MPP |
|
|