The default duration suffix (and hence duration
value) is set on the Schedule tab of the Options dialog box. |
 |
 |
Elapsed time is 24 hours a day, 7 days a week.
For example, a 7 elapsed day (7ed) task "Wait for paint to dry" could start
on a Wednesday morning and be complete by the following Tuesday
evening. |
 |
If you click on row #11 and then Ctrl+Click on
row #6, Project will link from the 1st selected task to the 2nd task
selected. You could also drag and drop a link from the
predecessor's bar to the successor's bar. |