|
|
|
 |
Open one
of the following
project files as the background for this lesson: |
LESSON_A3_END.MPP |
your own project file |
|
LESSON_B1_START.MPP |
sample project file |
|
|
|
Walkthrough |
|
|
 |
|
3m 45s |
|
|
|
|
| |
The first objective is to list the tasks that make
up the
scope and
deliverables of the project's definition. These will become the
summary tasks and
milestones that provide
strategic information about the project. The simplest way to
create these tasks is to list them within a
task-based view: |
|
|
| |
- From the View menu, choose Gantt Chart.
- On the first available row, enter the task's name, confirmed with
.

- Displayed as a one-day task commencing on the
project start date:

The other top level
tasks for this project are:
Publicity campaign.
Show arrangements.
Show opens.
These tasks can be added within
successive rows:

|
|
|
|
|
| |
| |
|
| Inserting new tasks
into a task list |
| |
|
| |
Once the
top level tasks have been created, additional tasks can be added
within the task list. These can be added to the base of the list, or
inserted within the list. For the Trade Show project, four tasks
need to be inserted between the Exhibit area and Publicity campaign top
level tasks.
These new tasks are:
Ready
to manufacture.
Manufacture booth.
Create
signage.
Design booth.
To add these tasks: |
|
|
| |
- Position the cursor by clicking on a task BELOW the desired
insertion point.
- From the Insert menu, choose New Task (or press the INSERT key),
creating a new blank
row:

- Enter in the task's name, confirmed with
:

- The new task is added within the existing
list:

- Additional tasks can be inserted by following
operations 1-3 and should be displayed as:

|
|
|
|
|
| |
|
|
| |
Tasks within a list are not always in an ideal
order. In the list above, the task 'Design booth' should be on row 2
and not row 5, as it should be the first task within the project to be
accomplished. As the
cell drag and drop option is selected by default within Microsoft
Project, this
task can be moved within the task list: |
|
|
| |
- Select the entire task by clicking on its
row heading:

- Drag the task to its new position as shown by
the line cursor:

- Then drop it into its new position:

|
|
|
|
|
|
|
Walkthrough |
|
|
 |
|
4m 01s |
|
|
| |
|
| Changing tasks into
milestones |
| |
|
| |
Within the Trade Show project two tasks aren't
really tasks at all. They signify that work has been accomplished
(or is about to commence), or a decision has been reached. These
tasks (which are referred to as
milestones) are:
Ready to manufacture.
Show opens.
To change these tasks from
normal tasks into
milestones: |
|
|
| |
- Select the task to change:

- Using the
spin control,
reduce the task's
duration to be 0 days as below (confirmed with
):

- Displaying the milestone:

- Repeat steps 1 and 2 for the task 'Show
opens' as shown below:

|
|
|
|
|
| |
| |
|
| Applying outlining
functions |
| |
|
| |
Within the Trade Show project, tasks 2 through 5
(Design booth - Create signage) should all be
subtasks beneath the
summary task 'Exhibit area'. As all newly-created tasks are
initially
normal tasks, an
outline must be created to contain subtasks within summaries. To achieve this: |
|
|
| |
- Select the tasks to become subtasks:

- Then click on Indent (
)
or from the Project menu select Outline followed by Indent.
- Making the selected tasks subtasks and the
task above them a summary task:

The two remaining tasks; 'Publicity campaign'
and 'Show arrangements' need detail adding beneath them as well. You
will need to create the following tasks beneath 'Publicity campaign':
- Prepare mailing list.
- Create invitations.
- Print invitations.
- Post invitations.
and the following tasks beneath 'Show
arrangements':
- Administration.
- Hold team briefing.
- Ship to venue.
- Construct booth.
Within the Gantt chart, these subtasks and
summary tasks should look like this:

|
|
|
|
|
|
|
|
|
 |
Save your project with the
following filename: |
LESSON_B1_END.MPP |
|
|
|
© Project Learning International Limited 2007 |
|
|
further info... |
The
interactive lesson above is just one of many lessons,
exercises and references within the complete Project
Mentor learning system. For further information,
please use the buttons to the right... |
|
|
|
|