|
On
Friday 15th September 2000, approximately 4.5 billion television viewers
will watch the opening ceremony of the XXVII Olympiad. They will see the
largest outdoor venue in modern Olympic history - Homebush Bay's Olympic
stadium. The 760-hectare site at Homebush Bay is located near
the demographic and geographic heart of Sydney. The area is located on the
western fringes of Sydney's Central Business District, and prior to
European settlement was occupied by Aboriginal people living in the tidal
wetlands and thick woodlands surrounding Homebush. Since the site's
initial development, the land has undergone a multitude of uses such as a
racecourse, brickworks, armaments depot and believe it or not, a State
Abattoir and Meatworks. Unfortunately, during the 1960s and 1970s, certain
areas of Homebush Bay became contaminated as a result of uncontrolled
dumping of household and commercial waste. Following Sydney's successful
bid for the 2000 Olympic Games, this provided the New South Wales (NSW)
Government, an impetus to commence the clean up and renewal of the area. |
|
The Olympic
Planning Process
The NSW Government realised at
an early stage of the planning process that there was an important need
for an overriding authority to co-ordinate and pull together the efforts
of various government departments, private sector builders and developers
who were involved in the construction of Olympic venues. The OCA was
created out of that need and was tasked with the responsibility for
planning and managing the programmes of work to ensure they were ahead of
time and within budget. The planning for the Olympics and Paralympics took
place within a framework of legislation and regulation and was required to
take into consideration environmental and conservation issues for the Homebush Bay area. One such major programme undertaken by the OCA was the
construction of the Sydney 2000 Olympic stadium - Stadium Australia. During a recent visit to Homebush Bay in Sydney, Australia, I managed to
meet up with the Programme Director for Stadium Australia - Mr. Paul
Gilbertson, who works for the OCA. His portfolio included the overall
management of the Sydney Super Dome construction, which will host
Gymnastics and Basketball during the Games, plus surrounding show grounds
and IBIS and NOVOTEL hotels and car parks. Construction of stage 1 of
Stadium Australia (Olympics mode) was officially completed in March 1999. Following the Games, the Stadium Australia Group will operate and maintain
the Stadium until 2031 under a lease agreement from OCA. After this
period, ownership will revert to the NSW Government and thus ensuring its
long-term future beyond the Olympic Games. During my interview with Paul
Gilbertson, I gained an insight into how these major construction
programmes were planned and managed, together with the general day-to-day
challenges that were faced. Stadium Australia In the early stages of the
programme of work, consultants at KPMG produced cost models for the
proposed work and submitted a report to SOCOG and OCA. SOCOG and OCA
produced a brief from this information, which was made accessible to all
tendering parties. Within the brief it stressed the importance of a
long-term plan for the future use of Olympic venues and that Stadium
Australia would be subject to rigorous environmental guidelines during its
construction process. Three approaches were considered during the bid
process, 'D & C' (Design and Construction), 'D, C & F' (Turnkey
Design, Construct and Finance) and 'BOOT' (Build, Financed and Operated). Following the completion of the tendering process, Obayashi
Corporation/Multiplex Constructions were awarded the construction work
adopting the BOOT approach.
Planning the work
The construction of Stadium Australia was
to be a very large and high profile programme of work, with the timings
for deliverables and Milestones being crucially important. As a result of
this, OCA ensured that during the programming of the major buildings, they
were designed to match both industry capacity and to give sufficient
lead-time to solve any major problems that could potentially occur. Planning the Olympic stadium construction was broken down into 'major
packages' of work, so that it could be controlled more effectively. Additionally, this approach also helped to reduce the number of
communication interfaces that could exist in a programme of this
magnitude. During the interview, Paul Gilbertson pointed out that as the
programme got underway it became increasingly a challenge of
communication, as it involved many parties with differing agendas who had
to be managed effectively. He made the comment that it became a real task
of 'effective co-ordination', - a classic example of Programme Management
to you and I. During the planning process, the building contractors
nominated major Milestones that were clearly defined and measurable at six
monthly intervals. |
|
The agreed
Milestones arrangement attracted liquidated damages for any potential
losses incurred, which were refundable if the contractor 'caught up' at
future planned Milestones. During the life of these large construction
programmes, OCA were not responsible for the day-to-day construction work
and therefore did not have direct control over resourcing and progress. This was dealt with by the building contractors at project plan level, but
with the lower level plans being submitted on a regular basis to the OCA
programme team, to enable the overall programme plan to be updated. Furthermore, with regard to the Programme/Project Management aspects, Paul
Gilbertson commented that it took more OCA personnel to MANAGE the
programme, than was initially envisaged at Initiation Stage. During the programming process, the building contractors provided
lower level linked Gantt Charts to represent their individual 'packages of
work' using Microsoft Project and submitted these to the OCA programme
team. It was found that because of the level and nature of the task
dependencies, these could not be regarded as being 'rock solid' and did
become somewhat difficult to model at this detailed project level. Once
the individual package plans had been received from the building
contractors, PRIMAVERA was then used to pull all the individual contractor
plans into one overall programme plan, to be assessed by the OCA team for
any potential impact to the overall programme.
Lessons learnt
Numerous lessons were learnt from these
high profile construction programmes. Firstly, as part of the agreement
with the building contractors, OCA had the option to remove the building
contractor at any time during the construction process. This in itself
acted as a very strong management tool. Secondly, an Advisory Committee
was established, which clearly helped resolve any important issues that
occurred during the programme of work and in turn helped to reduce the
risk of these issues delaying the programme - time being of great
importance to this particular programme of work. Thirdly, possessing
clearly identified and measurable Milestones, with potential liquidated
damages applied to any Milestones that delivered late, clearly helped to
focus the building contractors and to provide a powerful management tool
to OCA.
Pride
During the interview, you get a great sense
of Paul Gilbertson's pride in what has been achieved at Homebush Bay. The
facts and figures bear this out. The construction of Stadium Australia
began in September 1996 with a final development cost of A$ 690 million
(£460m): three months earlier than proposed in Sydney's Games bid and
eighteen months before the commencement of the Games themselves. The SOCOG
Committee has been widely criticised by the parochial media for not
sufficiently favouring the host country in its allocation of tickets. This
has been one criticism amongst a number that has accompanied the media
hype, during the publicity build-up to the Games. Unlike SOCOG, who
recently have been facing allegations of bribery and corruption in the
world press, OCA seem to have quietly gone about their business and
delivered what they were tasked to deliver within time and budget. Naturally, parallels can be drawn with our own Millennium Dome in London,
which seems to be a good example of how not to manage a high profile
programme of work. At an estimated cost of £800 million, continual press
reports of Milestones not being met, requirements not signed off, lack of
general communication and co-ordination with budgets constantly being
revised after work has commenced - a recipe for disaster. Furthermore, the
question does need to be asked, as to whether Australians will get more
long term value for money out of Stadium Australia, when compared with our
own Millennium Dome - we will all have to wait and see… |